Construction of the gas turbine power station of Uralsk | October 2008 - December 2010 |
Signing The act of commissioning the object. | April 1, 2011 |
Registration of the object in the justice authorities of the Republic of Kazakhstan | April 25, 2011 |
Familiarization visit Of the President of Kazakhstan Nursultan Nazarbayev to the Gas turbine power station of Uralsk | September 14, 2011 |
Type-GTU of the cogeneration cycle, exhaust gases from the GTU are supplied to waste heat boilers to produce steam or hot water used for technological needs or for heating. This is the most common technological scheme, as well as the most economical. The fuel utilization rate in this scheme reaches 90%.
The gas turbine power station of Uralsk is a modern, high-tech station, requiring virtually no human intervention.
The entire station is managed and maintained by 50 people.
Management and monitoring of the main components and units is automated and is carried out from the control room based on sensors and specialized programs from the leading Austrian company - Bernecker and Rainer.
The work of the gas turbine power station is operated by the Automatic control system and control of technological processes (APCS).
The gas turbine unit is controlled by an automatic control and control system (ACS). To control the installed equipment, there is a control and control system (SCU) based on modern microprocessor technology of the APCS. Installation of the automated control system was carried out by «Yuzhtransenergo» PJSC (Zaporozhye, Ukraine).
Automatic control system-a system that works in real time, allowing the operator-technologist to ensure effective management of the process of generating heat and electricity, facilitating the work of operational personnel.
In 2013, the gas turbine power station of Uralsk reached self-sufficiency due to the achievement of the design capacity (48 MW).CH.). The company is able to independently service a Bank loan subsidized under the "Business Road map -2020" program. Estimated net income is 15% in 2014 with an increase to 23% by 2018.
Profitability can be significantly increased by: